Matters needing attention in fiber optic cable cutting

Oct 10, 2022 Leave a message

Submit the cutover application report in advance according to the cutover reporting time limit, and in the cutover plan, specify the section name, trunk disconnection, cutover reason, location, time, cooperating personnel, division of labor for cutover personnel, vehicles, instruments and equipment, and the cutover plan. The following items should be paid attention to during the cutover:

1) Selection of cutover points

The cutover point should choose the original joint position as much as possible, taking into account the transmission index, the convenience of operation and other factors, so as to reduce the joint loss caused by the cutover as much as possible. If the cutover point is far away from the original cutover point and the transmission index allows, you can place the cutover point in a suitable position in the routing.

2) Division of labor for cutover personnel, vehicles, instruments and equipment

● The list of personnel, contact information, vehicles and instruments for the implementation of the connection group and test group should be arranged reasonably, and personal factors and on-site factors should be fully considered. In the case of insufficient local manpower, the superior department should be contacted as soon as possible to request reinforcements on personnel, vehicles, instruments and equipment. It is required to have a backup instrument at the cutover site and the test site, so that it can be dispatched in time when a certain instrument fails during the cutover process.

● Implement the specific responsibilities of the cutover commander, the responsible personnel and cooperating personnel of the succession group and the test group, and clarify the specific contact method. Generally, at least two or more contact methods should be considered to ensure smooth communication between the cutover points and between the cutover points and the test points during the entire cutover process.

3) Cutover scheduling scheme

To fully understand the openness of the system, the status of the spare core and the core chromatogram of the new/old cable. It is necessary to work out the sequence and steps of detailed scheduling, proofreading, identification, and connection of each fiber core and each system, and strive to restore the circuit in the shortest time.

When there is a spare bundle tube in the optical cable, the spare bundle tube should be used for scheduling. It is also possible to schedule the open systems in several bundle tubes together, leaving one bundle tube for scheduling. When the spare bundle tube cannot be guaranteed, as long as there are two spare fibers with good performance in the optical cable, it can meet the needs of fiber core scheduling with service cutover. The priority order of circuit scheduling is used to schedule important service circuits.

4) Emergency dispatch plan

Due to the use of service cutover, there are certain risks. In order to avoid accidents in the process of optical cable stripping and splicing, resulting in circuit interruption, or business interruption due to other reasons, a detailed circuit scheduling emergency plan should be formulated before the cutover. If the optical fiber is interrupted due to misoperation, the disconnected fiber should be reconnected as soon as possible, or the circuit should be adjusted to quickly restore the system. Therefore, it is essential to formulate detailed troubleshooting methods and emergency contact methods in the emergency dispatch plan.